Week 1:

Engineer to prepare plan after contract signing and payment of deposit

Week 2:

Pool plans submitted to local authorities

Week 3:

Mark out of pool. Excavation and construction of concrete pool shell.

Week 4, 5, 6, 7:

Concrete curing time. This is when the owner is to erect the fence and have wiring in place for the filter and pool lighting.

Week 8:

The pool coping is affixed first. The pool interior is completed and the pool filled with water.

PLEASE NOTE:

Installation of interior and filling of pool with water cannot take place until the pool fence has been erected, then inspected and approved by certifier.

ALSO

Concrete surrounds should not be undertaken until the pool coping has been installed. When the pool is full of water, a HANDOVER of the pool takes place where the owner is coached on workings of the pool and equipment. Chemicals are added to the pool. Avoid swimming in the pool for 24 hours.

The checklist provided above is designed to guide our customers through the building stages of their swimming pool. Please note that this is a guide only and outside influences such as weather and supply of materials can change the finishing time. If the pool is to be completed for a special occasion…. Please allow for unexpected delays to avoid dissapointment.

Bombora Pools offer this checklist so you may enjoy your pool building experience with us.